FOR PEBBLE BEACH COMPANY PROJECTS |
Return to |
Return to |
Return to |
Click HERE for a hyperlink to the related attachments referenced at the end of these letters (below) |
11-18-04 - During the Public Hearing, the County Subdivision Committee and Planning Department ignored California Coastal Commission Staff advise and recommendation, "...that the project (PB Co. applications for major construction projects in Del Monte Forest) not be heard until after there have been final Coastal Commission decisions on the LCP (Local Coastal Plan to include Measure "A" zoning and other changes) and coastal permit amendments (to previous Spanish Bay development) that would be required for the [PB Co.] project to proceed.
|
STATE OF CALIFORNIA -THE RESOURCES AGENCY
- - - -ARNOLD SCHWARZENEGGER, Governor November 17, 2004 Subject: Monterey County Public Hearings on "Pebble Beach Company's Del Monte Forest Preservation and Development Plan" Project (PLN 010254, PLN 010341, and PLN 040160) Dear Mr. McCue: Thank you for forwarding the County Subdivision Committee hearing notice to our office last week regarding the above-referenced project, as well as forwarding the County's staff report for that hearing to our office this week. According to these materials, the County Subdivision Committee intends to have a hearing on the Pebble Beach Company project on November 18, 2004, to be followed by Planning Commission and Board of Supervisor hearings starting in January 2005. The Subdivision Committee is being asked to recommend (to the Planning Commission and Board of Supervisors) that the project, including required changes to the County's Spanish Bay permit, be approved. We continue to strongly advise that the project not be heard until after there have been final Coastal Commission decisions on the LCP (Measure A) and coastal permit (Spanish Bay) amendments that would be required for the project to proceed. We note that the draft CEQA documents acknowledge these Coastal Commission review requirements, and we further note that the County's staff report also acknowledges these requirements. However, the current staff recommendation then proceeds to identify a portion of the project that could proceed absent any further Commission action on Measure A and Spanish Bay, and a portion of the project that cannot. This is implemented by suggested conditions of approval that are structured to require evidence of Commission certification of Measure A and approval of the Spanish Bay coastal permit amendment (prior to issuance of grading and building permits) for only a segment of the project. Presumably the intent is to allow the rest of the project to proceed without such Commission action. In both cases, such approval appears structured to precede submittal of Measure A. Such an approach is problematic and we strongly recommend that project approval not precede required Commission approvals, and not be segmented in this manner. It is inappropriate for project approval to be conditioned on future Coastal Commission approvals, and it is inappropriate for an interrelated project of this magnitude to be segmented into a portion that requires Measure A certification and a portion that purportedly does not. We disagree with the analysis that a portion of the project is consistent with the existing LCP. Furthermore, conditioning the project approval in whole or in pan in this manner presupposes that the Commission will certify the Measure A LCP amendment as submitted, and will modify the Spanish Bay coastal permit as proposed. As you are aware from our previous comments, we continue to have serious reservations about the project and the LCP amendment, and it is unwise to presume that LCP and permit amendments would be approved as submitted. In short, the outcomes of a Measure A amendment to the LCP and an associated amendment to the Spanish Bay coastal permit are uncertain, and the specifics of these outcomes will necessarily affect the manner in which all aspects of the project (both those deemed consistent and those not in the staff report's segmentation of the project) can be found consistent with the LCP and past permits. County decision makers at each level need to have the benefit of this information prior to making final decisions on the project. Without it, their understanding of this large and contentious project, and their discussions on the merits of it in relation to the LCP, will be significantly hampered. Because of this, a final County action on the project prior to final Commission action is not appropriate. Given the inextricable link between the LCP amendment and the proposed project, we understand why the County would want to use the ongoing CEQA review process to help develop information both for the permit review and to support an LCP amendment submittal. To a point, such a combination makes sense as a way to pool scarce County resources on common questions. However, it is now time that these review processes be separated. To do otherwise seems to us to be poor use of time and resources because any series of County hearings on the project now will be without the benefit of knowing what the Coastal Commission will do later. In other words, if the County' holds a series of hearings leading to an action now (as is the intended approach according to the notice and staff report that we received), these hearings will not have the benefit of critical information for making coastal permit decisions. Any "final" decisions made after this series of hearings will need to be revisited at additional hearings following Coastal Commission actions, and are thus premature. Moreover, even the existing "known" body of information is in question, and this also indicates that decisions on the project now would not be prudent. Specifically, the aforementioned CEQA documentation, and the current County staff report analysis that incorporates and relies upon it, is incomplete and has been compromised by an incorrect evaluation foundation. This is particularly the case in terms of the DEIR's identification of environmentally sensitive habitat area (ESHA) and its ESHA impact evaluation methodology (please see our March 22, 2004 letter on the original DEIR and our November 10, 2004 letter on the PRDEIR for specific reasons for this). We continue to highlight that the DEIR's evaluation has not been sufficiently inclusive of Del Monte Forest ESHA, and has not been clearly premised on Coastal Act and LCP requirements That impacts to ESHA be avoided. Likewise, and related to County staff report references to legal lots and certificates of compliance (whether conditional or unconditional), we have not seen supporting documentation for determining the number of legal lots of record that are a part of this application (most recently requested in our DEIR comments), and thus there remains significant uncertainty in this regard. Remember, too, that conditional certificates of compliance require coastal development permits. Any decisions on whether a certificate is conditional or unconditional is also a question of whether a coastal permit is required and subject to Coastal Commission concurrence in this regard. In sum, as we have advised since March of this year, and most recently reiterated in our November 10, 2004 PRDEIR comments, we continue to recommend that the DEIR be revised and recirculated for public review and comment. We strongly recommend that hearings (if there arc any at all) at this time at the County level be limited to perfecting supporting information for the LCP amendment (including perfecting project CEQA information), and that any such hearings explicitly not include any decisions on the project in advance of final Commission actions on both the Measure A LCP amendment and the Spanish Bay coastal permit amendment. We continue to believe that good planning and public policy require that the review process for the LCP amendment and the Spanish Bay coastal permit amendment conclude and precede any coastal permit decisions on the project itself. To do otherwise appears to us a poor use of scarce staff and decision-maker time and resources, would diminish die value of the project deliberations at each decision-making level leading to a final Board decision, and would only serve to unnecessarily complicate and delay an ultimate decision on the project itself. That said, if the County decides to proceed with the project review schedule and recommendations noted in the hearing notice and staff report despite our recommendation, please note that any ultimate Board approval of the project should be considered tentative and cannot be forwarded to the Commission as a final action. At a minimum, the Board would have to hold at least one additional coastal permit hearing (preceded by at least one hearing on the LCP in the case Measure A is not approved by the Commission as submitted) after Coastal Commission action to take final action on the coastal permits and then send them to the Coastal Commission to start the ten-day appeal period. This needs to be made explicit in any staff report and/or approval documents, and any approval conditions requiring future Coastal Commission actions should be omitted. In the case that the County proceeds with hearings, please provide this letter, and our DEIR and PRDEIR letters, to the Subdivision Committee members, Planning Commissioners, and Supervisors for those hearings. We hope that this letter has again helped to frame the LCP and coastal permit context for this project. We, like the County and the Pebble Beach Company, are anxious to come to final resolution on the project and on the LCP. As we have said before, the proposed project is one of the largest to be proposed in the Central Coast in recent years, it involves significant impacts to important coastal resources, and it remains the subject of considerable public debate. It would be unfortunate if the final outcome was unnecessarily hindered and complicated by a flawed process. We are optimistic that this can be avoided. As always, feel free to contact me if you would like to discuss this matter further. cc: Pebble Beach Company |
STATE OF CALIFORNIA -THE RESOURCES AGENCY
- - - -ARNOLD SCHWARZENEGGER, Governor November 10, 2004 Thom McCue Subject: Partial Revision of the Draft Environmental
Impact Report titled "Pebble Beach Dear Mr. McCue; Thank you for forwarding the above-referenced Partial
Revision of the Draft Environmental Impact Report (PRDEIR)
TO our office for review. In sum, please note that we
continue to have serious reservations about the Local
Coastal Program (LCP) amendment necessary for Pebble Beach
Company's proposed project (Measure A), and the project
itself (see also our previous correspondence to this effect,
including our recent March 22, 2004 letter on the original
DEIR). As has only become clearer with the PRDEIR, the
proposed project would significantly and adversely affect
coastal resources, including significant environmentally
sensitive habitat area (ESHA) resources. This PRDEIR, like
the DEIR before it, neglects to identify all ESHA as ESHA,
and fails to account for the LCP and Coastal Act ESHA
requirements in this regard, including continuing a reliance
on mitigation as opposed to avoidance. The EIR's utility for
LCP amendment and project review is compromised as a result.
Nonetheless, we continue to provide comment here with the
intent of helping the County in its preparation of the
underlying information necessary for further project review
and discussion. We hope that these comments prove helpful in
this regard. CEQA Process PRDEIR I. The PRDEIR water impact evaluation appears to be
premised at least partially on limiting annual Cal-Am Carmel
River diversions from the Carmel River to 11,285 AFY per
State Water Resource Control Board (SWRCB) Order WR 95-10,
and on the effect of the project as related to current
withdrawals from the River. (b) The PRDEIR appears to indicate that Cal-Am has not
perfected a legal water right to 11,285 AFY from Carme1
River. As the PRDEIR indicates, SWRCB has indicated that
Cal-Am has legal rights to only 3,376 AFY (see also SWRCB
March 17, 2004 letter commenting on the DEIR), Please
provide a clear explanation of, and supporting
documentation for, Cd-Am's existing legal water rights
pertaining to Camel River. (c) The PRDEIR does not explain how (including from
what source) water will be provided to serve the proposed
project in the event Cal-Am cannot perfect a legal right
to its existing Carmel River diversions. This information
is necessary for understanding water impacts due to the
project. Please ensure that subsequent CEQA documents
include this information. (d) The PRDEIR does not make a compelling case that
existing withdrawals (nor the 11,285 AFY figure) are an
appropriate baseline from which to measure project
impacts. We note that the PRDEIR appears to acknowledge
as much (though the analysis baseline isn't changed in
light of this) when it indicates that existing
withdrawals both exceed Cal-Am legal rights and have
resulted in adverse biological impacts. Rather, we need
to understand the effect of the project related to the
estimated maximum amount of water that could be withdrawn
from the River without affecting River resource values
(fisheries and otherwise). Please provide this
information, including any supporting assumptions and
information as well as the most current recommendations
in this regard from the resource agencies involved
(including the California Department of Fish and Game
(CDFG), NOAA Fisheries, United States Fish and Wildlife
Service (USFWS), SWRCB, etc.). 2 It is clear from the PRDEIR that Cal-Am's withdrawals
from the Seaside Basin have increased in recent years, and
it appears clear from the PRDEIR that this has had and is
continuing to have an adverse impact on this groundwater
resource. (b) Similar to Carmel River resources, the PRDEIR does
not make a compelling case that existing Seaside Basin
withdrawals are an adequate baseline from which to
measure project impacts. Rather, as with Carmel River, we
need to understand the effect of the project related to
the maximum amount of water that could be withdrawn from
the Basin without affecting its resource value, If trends
indicate this figure to be changing (as indicated in the
PRDEIR where "safe yield" estimates have been lowered
just this year), then please extrapolate such trends in
this regard. Although it is not clear from the PRDEIR
whether the Basin's estimated "safe yield" (currently
estimated in the PRDEIR at 4.375 AFT) represents this
maximum potential withdrawal amount, at a minimum, the
project impacts as compared to the basin's safe yield
should be evaluated. Please provide this information
including any supporting assumptions and information as
well as the most current recommendations in this regard
from the resource agencies involved (again, CDFG, NOAA
Fisheries, USFWS, SWRCB, etc.). 3. The PRDEIR water impact evaluation also appears to be
premised at least partially on the Pebble Beach Company's
water entitlement agreement with the Monterey Peninsula
Water Management District (MPWMD). (b) It is not clear from the PRDEIR how or why this
agreement translates into a right to water; something
that is governed by water law and not by agreements made
between water management districts and private companies.
Please provide clear explanation of how this entitlement
translates into a water right. c ) It is not clear from the PRDEIR how or why the
agreement should be read to allow Pebble Beach Company to
use water that is not actually physically available. We
note that the agreement is based on two primary
suppositions: that the Pebble Beach Company will use less
Cal-Am water because it is using reclaimed water instead,
and that the entitlement of 365 AFY of Cal-Am water is
available. Pebble Beach Company has greatly reduced its
reliance on Cal-Am water for irrigation purposes, but in
only one year so far reached the target of 800 AFY saved,
upon which the agreed upon entitlement was based. If
reclamation efforts are not yielding expected water
savings, commitments to reserve water based on
reclamation may no longer be appropriate; particularly in
light of resource impacts to Carmel River and the Seaside
Basin due to existing (and proposed) withdrawals. It
appears that the agreement needs to be updated to reflect
the current impact (from withdrawals) and reclaimed water
use realities. This is particularly the case given that
the agreement's 365 AFY was apparently developed based on
estimates of Del Monte Forest buildout that do not appear
to have adequately accounted for the number of legal lots
of record and resource constraints on them otherwise (see
also March 22, 2004 comments in this regard), and was
developed well before the agreement itself. Please
provide a clear analysis of how and why the agreement
helps demonstrate a long-term water supply to serve the
project when even existing withdrawals of water are
leading to resource degradation and have not themselves
been legally perfected (see also above). Please also
provide evidence of input from MPWMD in this regard. (d) PRDEIR Table G.2-6 indicates that the Company has
used only 9.9 AFY out of an original agreement for 365
AFY. Please provide a breakdown for how the 9.9 AFY has
been allocated, including underlying information
documenting that amount of use for the projects to which
the allotment has been directed. 4. The PRDEIR relies in large part upon Recycled Water
Project (R-WP) Phase II improvements to offset water use
impacts due to the proposed project. (b) Except in very dry years, the PRDEIR indicates
that all water supplied for irrigation in the Forest
would be from recycled water (PRDEIR Table PI-6), and
refers to Appendix G for details and assumptions
supporting this. It is not clear to us from the PRDEIR
discussion how and/or why such irrigation use quantities
would be achieved, and we couldn't find a clear
explanation of this in Appendix G. Please provide a clear
explanation (including maps and figures) as to what
constitutes the irrigation use within the Forest to which
Table PI-6 corresponds, and please also clarify the
Appendix G explanation for why this would be the case.
Please also explain and provide a description of the
implementing mechanisms that would be used to ensure that
only recycled water is used in this regard. 5. Please modify the EIR's overall water supply impact
assessment (and mitigation framework), including that
relative to cumulative impacts, to address the above
comments, 6. We appreciate the PRDEIR's improved information
regarding indirect impacts to Yadon's piperia due to the
project, but we continue to disagree with the ESHA
identification and impact assessment methodology applied to
this federally-listed endangered species, The PRDEIR does
not identify Yadon's piperia and its habitat as ESHA. As we
have previously indicated, most recently in our March 22,
2004 letter, Yadon's piperia must be evaluated as ESHA and
impacts to this species avoided (we note here that all
comments regarding ESHA in our March 22, 2004 letter are
included in their entirety in this comment by reference).
Toward this end we cannot agree that project impacts on
piperia can be mitigated to a less than significant level.
According to the PRDEIR, the project would directly remove
36 acres of occupied Yadon's piperia habitat (and over
36,000 individual plants). Such project direct impact
includes removal of the world's largest known occurrence of
piperia at the site of the proposed golf course; an
occurrence appropriately recognized by the PRDEIR as
"considered important to the recovery of the species."
Project direct impacts in this regard represent destruction
of over a quarter of the known Yadon's piperia population in
the Forest and 21% of the known population in the world. In
addition, the PRDEIR indicates that the project would result
in indirect adverse impacts to 24 acres of occupied piperia
habitat (some 17,000 individual plants), and to 63 acres of
other potential piperia habhat. Accordingly, future CEQA
documents must be modified: to identify this species and its
habitat (see also below) as ESHA; must be premised on
avoidance of impacts to it; and must consider impacts to
Yadon's piperia to be significant and unmitigatable (please
also refer to our March 22, 2004 letter), 7. The PRDEIR begins to discuss the habitat conditions
for Yadon's piperia, including identifying Monterey pine
forest areas as potentially suitable habitat, but stops
short of providing conclusions or a useable methodology in
this regard. Rather, the PRDEIR relies on a methodology that
uses a 50-foot "occurrence buffer" around piperia plants and
clusters to determine an "occurrence area" for piperia.
Although the 50-foot buffer can be used to acknowledge some
"habitat" surrounding individuals found above ground, we
don't believe it can be used to meaningfully estimate
Yadon's piperia habitat areas. Rather, based on the
sensitivity of the species, it is incumbent upon the EIR
documents to clearly explain its habitat characteristics,
and to delineate the acreage of the area within which such
characteristics are present in order to quantify the area of
piperia habitat. In this respect, the PRDEIR appears to
support applying at least a conservative approach where
areas of Monterey pine forest are deemed to provide habitat
for piperia. Given the endangered status of the species, and
the fact that its known population is almost entirely
limited to the Del Monte Forest, such a cautious approach
seems appropriate here. Please provide an analysis of
Yadon's piperia habitat characteristics, and an evaluation
of the Forest areas containing such characteristics,
including updated maps and acreage tables. For any Monterey
pine forest areas deemed not to exhibit such
characteristics, please provide an explanation as to why
this is the case. 8. The PRDEIR is equivocal in terms of quantifying
indirect impacts to Yadon's piperia. As previously
indicated, we believe the most conservative approach would
be to analyze such indirect impacts as direct impacts if it
is not clear whether indirectly impacted resources will
continue to provide habitat/resource value due to the
project. In this case, the PRDEIR makes a compelling case
that indirect impacts will result in adverse impacts. This
is particularly obvious where large areas of habitat would
be fragmented by the project (e.g., as is perhaps most
obvious with the proposed golf course fragmentation as shown
in Appendix E Figure E- 9-YP). As such, the more
conservative approach is even more compelling in this case.
Please supplement the piperia impact analysis with tables
(modeled on PRDEIR Tables P2-1, P2-2, and P2-3) that
quantify indirect piperia impacts in this regard and that
can be used in to an additive manner (avoiding overlap with
direct impacts). 9. The PRDEIR indicates that the 2004 Yadon's piperia
survey methodology differed from that done in 1996, and that
this has resulted in a 2004 estimated acreage of occupied
habitat that is roughly 1/10 the size of that estimated in
1996. Please provide documentation indicating that the
California Department of Fish and Game and the United States
Fish and Wildlife Service concur with the methodology and
conclusions documenting Yadon's piperia habitat, including
that based upon the requested habitat characterization
method above. 10. The PRDEIR identifies two new areas - the Company's
Old Capitol and Aguajito (Jack's Peak) sites - where
conservation easements would be applied to offset project
impacts. The PRDEIR indicates that Yadons piperia surveys
would be done to identify that portion of these sites that
would be subject to such easement, Please ensure that any
such delineation process also be based upon habitat
characterization (as discussed above), and that it be clear
in any final documents what portion of these sites would be
subject to easement. For example, the PRDEIR indicates that
only one acre of the much larger Aguajito site would have
such an easement applied to it, though this seems
counterintuitive to us given that this area is covered in
Monterey pine forest that appears otherwise conducive to
Yadon's piperia. Please supplement any subsequent CEQA
documents with this information. 11, For any subsequent CEQA documents, please include
clear maps, acreage figures, and narrtive description of all
of the areas to which protective legal instruments (e.g.,
conservation easements, property restrictions, outright
dedications, etc.) would be applied, accompanied by the
relevant controlling text of any such instruments. Final CEQA Documents As you know, the proposed project is one of the largest
to be proposed in the Central Coast in recent years, it
involves significant coastal resources, and it remains very
controversial. Because of this, and to provide for the most
open and informed public discussion and debate on its
merits, we recommend that any final CEQA documents be
prepared in such a way that reference back to drafts is not
necessary. In other words, the final CEQA document would
include the final text and figures within which all changes
(in response to comments or otherwise) are reflected.
Comments and responses on drafts could be in a companion
final appendix document of some sort, but would not require
cross-referencing. The revised and recirculated DEIR
requested offers an opportunity to begin organizing the
document to be finaled in this way. Thank you for the opportunity to comment. As with our
prior DEIR comments, we hope that these comments help to
frame the LCP and coastal permit context for this project
and future development within the Del Monte Forest. We
continue to be available for consultation in this regard.
Although the project will no doubt remain controversial, we
continue to believe it is important that the County and the
Commission maximize the extent to which we are working from
a common understanding of the environmental baseline, and
potential project impacts, in our reviews. Good planning and
public policy require as much, and informed public debate on
the merits of LCP amendments and coastal permits is better
accomplished when this is the case. As always, feel free to
contact me if you'd like to discuss this matter further. cc: Pebble Beach Company
TOP
OF PAGE
CALIFORNIA COASTAL COMMISSION
CENTRAL COAST DISTRICT OFFICE
725 FRONT STREET, SUITE 300
SANTA Cruz, ca 95060
(831) 427-4863
Monterey County Planning and Building Inspection Department,
Coastal Office
2620 First Avenue
Marina, CA 93933
Company's Dcl Monte Forest Preservation and Development
Plan" (SCH Number 2002021130)
We were surprised to see a PRDEIR as opposed to a
completely revised DEIR as we previously requested. We
continue to believe that the CEQA evaluation process has
been compromised by an incorrect evaluation foundation -
most significantly in terms of the DEIR's identification of
ESHA and its ESHA impact evaluation methodology (please see
our March 22, 2004 letter on the original DEIR for specific
reasons for this). In particular, the DEIR's evaluation has
not been sufficiently inclusive of Del Monte Forest ESHA,
and has not been clearly premised on Coastal Act and LCP
requirements that impacts to ESHA be avoided. We continue to
recommend that a complete revised DEIR would be the most
appropriate means to rectify these problems. This is
particularly the case if, as the County has indicated in the
past, the CEQA document is being developed for both the
proposed project and The Measure A LCP amendment supporting
it. Moreover, due to degree to which the fundamental changes
necessary would lead to a substantial increase in the
severity of project environmental impacts, CEQA requires
recirculation in this case (including but not limited to
CEQA guidelines section 15088.5(2) and (4)). Please revise
the DEIR (in response 10 previous comments received as well
as information developed and comments received on this
PRDEIR) and recirculate it for public review and
comment.
We appreciate the depth of additional information developed
in the PRDEIR. Other than our basic CEQA objection described
above, we found the PRDEIR to be informative and helpful on
the limited subset of issues that it evaluated. That said,
other than our request for additional water data and our
request for additional information regarding potential
indirect impacts to Yadon's piperia (on page 5 of our March
22, 2004 letter), the PRDEIR does not otherwise respond to
the questions and comments from our March 22, 2004 letter.
Accordingly, any subsequent CEQA documents must respond to
all other comments in our previous letter, and our comments
here are limited accordingly. To the extent that there is
any question in this regard, then we incorporate our March
22, 2004 letter in its entirety as a part of this letter by
reference, and consider it to have been submitted on this
PRDEIR as well. We have the following comments specific to
the PRDEIR:(a) The PRDEIR omits a copy of SWRCB Order WR
95-10. Please ensure that any subsequent CEQA documents
include a copy of SWRCB Order WR 95-10, and any relevant
attachments, amendments, and/or other SWRCB documentation
affecting the order.
(a) The PRDEIR briefly touches on the types of
problems associated with overpumping of the Basin (such
as saltwater intrusion), but does not provide a clear
baseline description of the existing condition of the
Basin in this regard. Please provide information on the
Basin's water quality trends, including at a minimum a
clear description/assessment of the effect of historical
pumping levels on saltwater intrusion in the Basin, and
potential responses being considered (i,e., limits in
pumping, importation of water, etc.). Please provide any
supporting documentation and maps as well.
(a) The PRDEIR omits a copy of the agreement.
Please ensure that any subsequent CEQA documents include
a copy of the agreement, and any relevant attachments,
amendments, andlor other documentation affecting it.
(a) The PRDEIR omits an analysis of how project
impacts will be offset if Phase 11: (a) is not developed
for whatever reason; or (b) is less successful than
estimated. Given the track record with reclaimed water
use in the Forest (where use of same has not generally
achieved all of the potable water savings predicted, and
the PRDEIR indicates that approximately 30% of the RWP
water currently supplied is actually potable water), it
seems unwise to rely so heavily on such a mitigation
without some sort of mechanism for ensuring that expected
savings are achieved, and if they aren't, a companion
mechanism for offsetting shortfalls. Please perform an
expanded analysis and mitigation assessment that is based
upon a spectrim from complete success with Phase II in
effect down to it not being developed at all (i.e., The
current reclaimed water status quo). Such analysis should
include rational demarcation points for scenarios
in-between (e.g., using success rates of 25%, 50%, 75%,
etc), perhaps based on the current track record of
success with recycled water in the Forest.
The utility of final CEQA documents (for use by decision
makers and the interested public) is often compromised by
the use of a final EIR document that isn't actually "final"
but rather represents acknowledgement of a suite of changes
in response to comments received on a draft. Such a "final"
EIR necessitates painstaking and difficult cross-referencing
between documents to be able to understand a project and its
expected impacts. These difficulties are only exacerbated
when there are multiple and/or atypical CEQA documents and
substantial comments (such as in this case with a DEIR in
two parts, a PRDEIR so far, and a significant amount of
comments). The value of final CEQA documents for informing
public debate on projects is decreased in such cases.
State Clearinghouse (SCH # 2002021130)
TOP
OF PAGE
|